Day 35

Second day on the electrics and I think they have one more day to go before first fix is done. 

Data cables and sky will be run to the fireplace aka the av hub.   
    

Day 36

We have a door and some windows!  

   
The roof has started to be boarded out and the insulation is going in.   

 

Day 37

Boarding of the roof is now complete. Just need to board the steels. Not long and it will start to look more like a room. The floor still has to be levelled.  

 

Day 38

We have paid all that money on steels and we hide them in plasterboard.   

   
Day 39

Final push to get it all boarded out before it all gets plastered. The rooms are taking shape now.    
    
 

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Google photo

You are commenting using your Google account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s